How long flooring installation takes depends on the product, the size of the job and what has to happen before the first plank or carpet goes down. The days the crew spends in your home are often only part of the calendar. Acclimation, subfloor preparation and adhesive curing can add time around those days. The schedule that applies to your rooms is the one in your written estimate.
Also see engineered hardwood vs laminate if you are still choosing between the two.
At PI FLOOR & BLINDS we sell and install solid and engineered hardwood, laminate, vinyl plank, carpet, stair runners, baseboards, stair nosing and rubber flooring in Victoria, BC. Our own crews — typically five or six of them — complete about 100 projects a year. We do not refinish or repair floors, and we do not sell area rugs.
The calendar is longer than installation day
Think of the project in stages, not as a single appointment:
- A free in-home estimate, then your product choice.
- Ordering and delivery of the flooring, underlay and trim. Lead time varies by product and stock; we will tell you what is available when we quote the job.
- Preparing the rooms — furniture, appliances, access and indoor conditions. See our installation preparation guide.
- Acclimation, when the manufacturer requires the material to sit in the home first.
- Subfloor preparation, if the existing floor has to come up or the surface needs levelling.
- Installation of the floor, transitions, baseboards and stair nosing, and any stairs.
- Curing time, when an adhesive has been used, before regular traffic and furniture go back.
What changes how long the crew is in your home
Square footage, the number of rooms and the layout all matter. So do stairs, doorway transitions, and whether old flooring has to be removed. A click-together vinyl or laminate floor over a flat, dry subfloor is a different day’s work than a nailed or glued hardwood floor, or a job that needs levelling compound first. We include the planned install dates in your written estimate. If something unexpected turns up under the old floor, we discuss it before any extra work goes ahead.
Acclimation can add days before installation starts
Acclimation — also called conditioning — means letting the flooring reach the temperature and moisture of the room where it will live. There is no single waiting period for every product. Follow the instructions for the floor you buy.
The National Wood Flooring Association (NWFA) defines this as aligning the wood flooring with the environment. If the flooring arrives already at the moisture content that matches normal living conditions and the subfloor, and those conditions are being maintained, the NWFA says the floor may be installed immediately. If not, it should be conditioned until it is compatible. We measure rather than guess: actual conditions in a Victoria home can differ from published coastal averages.
Manufacturer instructions on products we sell include:
- Goodfellow solid hardwood: at the job site at least 72 hours, or as long as needed to meet moisture-content requirements. Keep the site at 16–27°C and 40–55% relative humidity for a minimum of five days before any Goodfellow product is installed. Store boxes in the installation area, not on concrete or against outside walls.
- Eurostyle Novabelle engineered hardwood: in the room at least 48 hours, at 18–23°C and 40–60% relative humidity.
- Twelve Oaks engineered hardwood: acclimated once it reaches moisture equilibrium with the job site. Keep 35–55% relative humidity and 18–27°C for 48 hours before, during and after installation. Twelve Oaks also requires HVAC to be running at least 14 days before, during and after installation.
- Harbinger No-Stick Shurlock vinyl: at least 48 hours in the installation room at a constant 18–25°C, maintained during installation and for 24 hours afterwards. Harbinger glue-down LVT: a minimum of 18°C for 48 hours before, during and after installation.
- Eurostyle Eurotrend laminate: unopened packs in the installation climate for 48 hours beforehand, at 15–30°C and around 40–70% relative humidity.
- CRI 105 (Carpet and Rug Institute, residential): carpet and installation materials should acclimate in the area for a minimum of 24 hours at 18–35°C. Keep HVAC in the stated range for at least 48 hours before, during and 72 hours after completion.
Victoria’s wet season makes steady indoor heat and humidity especially important. Keep the house at normal living conditions, stay within the humidity range on your product, and do not store boxes in a cold garage or a damp crawl space.
Subfloor work can extend the schedule
If the subfloor is out of flat, damp or unsound, preparation has to happen first. Levelling compounds also have to cure for the time their manufacturer specifies before the new floor can go down. That cure window is why a job that looks like “one install day” sometimes needs an extra visit. Our underlayment and subfloor preparation guide explains what we check.
When can you walk on the new floor?
This depends on the product and the installation method, not on a generic rule.
- Twelve Oaks glue-down engineered hardwood: avoid foot traffic and furniture for 24 hours, and only install baseboards after the adhesive has cured.
- Harbinger glue-down LVT: light foot traffic after 12 hours and regular traffic 24 hours after the work is finished. Do not wash or polish the floor for at least 48 hours. Keep the room at a minimum of 18°C and no more than 65% relative humidity for 72 hours after completion.
- CRI 105, for carpet installed with field-applied adhesive: restrict traffic to installation personnel for a minimum of 24–48 hours so the adhesive can cure.
For click-together vinyl, laminate, floating or nail-down floors, and for stretch-in carpet, the traffic rules are set by that product’s instructions. We will tell you at the walk-through when you can use each room. Lift furniture rather than dragging it, and use felt pads.
Stairs, trim and what happens after
Stair runners, full stair carpet and stair nosing are planned with the main floor, because finished step heights have to stay consistent. Baseboards and nosing are part of what we sell and install. If you are planning stair carpet or a runner, see our carpet installation page.
PI FLOOR provides a 1-year warranty on installation workmanship. The product warranty comes from the manufacturer. Typical supply and installation is CAD 7–10 per square foot; stairs, removal and unusual subfloor work are extra. See our flooring installation cost guide.
Book a timeline that matches your home
Visit the showroom or book a free estimate. Free estimates cover Greater Victoria, including Colwood, Langford, Sooke and Metchosin. They are not offered in Highlands, Duncan or the Cowichan Valley. Call 250-590-0030.
Showroom: 100-4500 W Saanich Rd, Victoria, BC V8Z 3G2. Phone: 250-590-0030.
Frequently Asked Questions
How long does flooring installation take?
It depends on the product, the size of the job, acclimation, subfloor preparation and whether adhesive has to cure. The days the crew is in your home are set out in your written estimate.
How long does vinyl plank installation take?
Laying time depends on the area, layout and subfloor. Harbinger No-Stick Shurlock vinyl should acclimatize for at least 48 hours. Harbinger glue-down LVT allows light traffic after 12 hours and regular traffic after 24 hours.
How long does hardwood floor installation take?
Hardwood often needs more conditioning time than vinyl. Goodfellow solid hardwood should be on site at least 72 hours, with the home at 16–27°C and 40–55% humidity for at least five days before installation. Eurostyle Novabelle should sit in the room for at least 48 hours.
How long should flooring acclimate before installation?
Follow the manufacturer. On floors we sell, that is often at least 48 hours, or at least 72 hours or until moisture content is right for Goodfellow solid hardwood. The NWFA says wood that already matches in-use and subfloor moisture may be installed immediately. Carpet under CRI 105 should acclimate for a minimum of 24 hours.
When can I walk on my new floor and move furniture back?
After a glue-down job, plan on restricted traffic: Harbinger LVT allows light traffic at 12 hours and regular traffic at 24 hours; Twelve Oaks glue-down engineered asks you to wait 24 hours. For adhesive-installed carpet, CRI 105 restricts traffic to the installers for 24–48 hours. Lift furniture and use felt pads.
Does removing the old floor add time?
It can. Removal, disposal and any levelling underneath are not automatic in every quote. Confirm the scope in writing. Levelling compound must cure for the time its manufacturer specifies before the new floor goes down.
Do you install flooring in Victoria, BC?
Yes. Book a free estimate or call 250-590-0030. Free estimates cover Greater Victoria, including Colwood, Langford, Sooke and Metchosin, not Highlands, Duncan or the Cowichan Valley. Our workmanship is covered for one year; the product warranty comes from the manufacturer.